Step 1 |
Receipt of Customers Purchase Order |
| Upon receipt of work a work order , the lab manager determines and
evaluates customer specifications and test procedures. |
Step 2 |
Receipt of Customer Equipment |
| Depending on customer location, PCI will accept delivery or pick up
customer equipment at their facility as agreed upon prior to shipment. |
Step 3 |
Identification |
| Each unit received will be ID tagged and barcode affixed. The ID tag is a
traveler card that displays customers purchase order number and barcode number.
The barcode label is to maintain tractability throughout the repair process. |
Step 4 |
Unit Test Procedure |
| Prior to power up, a defined set of test procedures and O.E.M.
specifications will be provided to the performing technician. Using this
procedure, the technician will determine the initial failure, and list the
components needs or actions taken to restore original operating specifications.
Individual unit requirements, such as upgrades or specific parts vendors , are
previously planned by the lab manager in co-ordination with customer
engineering. |
 |
Step 5 |
Repair |
| The damaged component or cosmetic discrepancy will be repaired by a repair
technician and each repair process is recorded and signed off on traveler card. |
Step 6 |
Inprocess QC |
| Each repair and all work is inspected and approved by in process QC
personnel before the unit is further tested. |
Step 7 |
Unit Test #2 |
| After repair, the unit is powered up and tested under minimum, nominal, and
full load conditions to insure compliance with customers specifications, and
the card is initialed by the test technician as having passed U.T. |
Step 8 |
Burn-In |
| After passing U.T. , the unit proceeds to burn-in where the unit will be
subjected to a 24 hour test inside PCIs temperature controlled burn-in
chamber. This chamber simulates actual field conditions for an extended time
period. After successful burn-in, the unit is returned to the lab for
acceptance testing.
|
Step 9 |
Acceptance Testing |
| After burn-in, the unit is thoroughly tested under load specifications on
PCIs variable electronic load banks. All original operating
characteristics are confirmed and the traveler card is signed off by the
performing technician. |
Step 10 |
Data Log |
| After final QC, all important data is logged into the failure redundancy
database. This statistical information is used to help establish and improve
processing time and determine pricing information.
|
Step 11 |
Quality Assurance Inspection |
| To assure maximum.management of quality effort, the quality manager reports
directly to the lab manager, and has the complete authority to install all QC
procedures required, such as designated parts, Vendors, UL requirements,
shipping requirements and controls. This insures total quality through out all
phases of the repair process. The traveler card is finally signed off by QC and
the unit is readied for shipment back to the customer. |
Step 12 |
Shipment |
| Following final QC, travelers are doubled checked and all processes are
filed in a database. This gives the customer and PCI a permanent record that is
accessed at any time and/or provide a detailed cost or failure analysis.
Handling procedures will assure that all equipment will be protected from
damage during all phases of the repair process. Preservation, packing, and
shipping controls will be utilized during storage and shipments. |